Northland Pioneer College—Whiteriver Center

Owner: Northland Pioneer College
Contract: $1,421,361.00
Square Foot: 7,500
Location: Whiteriver, AZ
Job Summary:
This project entailed building a 7,500 SF CMU building for the campus center, extensive entry drive, parking/lighting, and associated utilities. The building included full computer networking, laboratory, and a library security system. The specifications required excavation to bedrock (4-16 FT), lime stabilization, and backfill. The excavation/stabilization/backfill were all accomplished in 3 weeks, allowing the project to proceed on schedule. Close supervision and monitoring of the project provided completion on schedule and under budget.